BC Hydro seeking input into Site C consultation process

Site C construction reaches 100-day mark

Categories: BC, Hydroelectricity

FORT ST. JOHN – This week marks 100 days of construction on the Site C Clean Energy Project in northeast B.C. In the first 100 days of construction, w…

Read
Dynamic message board signs will advise motorists of local fog and road conditions, construction advisories as well as being part of the provincial Amber Alert program.

Enhancing transportation infrastructure | Site C

Categories: BC, Hydroelectricity

As part of a community agreement between BC Hydro and the District of Taylor, BC Hydro committed to specific mitigation measures, including those that…

Read
BC Hydro seeking input into Site C consultation process

Agricultural stakeholder consultation | Site C

Categories: BC, Hydroelectricity

Framework for an Agricultural Mitigation and Compensation Plan From November 23, 2015 to January 29, 2016, BC Hydro, the Ministry of Agriculture and t…

Read
BC Hydro seeking input into Site C consultation process

BC Hydro donates $200,000 to The Salvation Army in Fort St. John

Categories: BC, Hydroelectricity

FORT ST. JOHN – The Salvation Army today unveiled a plaque recognizing BC Hydro’s $200,000 donation to The Salvation Army’s Northern Centre of Hope in…

Read
BC Hydro seeking input into Site C consultation process

BC Hydro awards Site C worker accommodation contract to ATCO Two Rivers Lodging Group

Categories: BC, Hydroelectricity

VANCOUVER – BC Hydro announced today that it has signed a contract with ATCO Two Rivers Lodging Group for the design, construction, partial financing,…

Read
BC Hydro seeking input into Site C consultation process

Job fairs and business-to-business networking sessions to be held in the Peace Region

Categories: BC, Hydroelectricity

FORT ST. JOHN – The B.C. Chamber of Commerce and BC Hydro are hosting job fairs and business-to-business networking sessions in the Peace region in Oc…

Read
BC Hydro seeking input into Site C consultation process

Protecting Bald Eagle nests | Site C

Categories: BC, Hydroelectricity

BC Hydro and its contractors will monitor and take great care to avoid or mitigate effects on active Bald Eagle nests during Site C construction. No a…

Read
BC Hydro seeking input into Site C consultation process

BC Hydro awards Site C contract for north bank site preparation activities

Categories: BC, Hydroelectricity

VANCOUVER – BC Hydro announced today that it has awarded a contract to Morgan Construction and Environmental Ltd. for preparation activities on the no…

Read
BC Hydro seeking input into Site C consultation process

Construction notification letter | Site C

Categories: BC, Hydroelectricity

BC Hydro is collecting your name and email address in order to send you email updates about the project and/or construction bulletins on the Site C Pr…

Read
BC Hydro seeking input into Site C consultation process

Job fairs postponed to September 2015

Categories: BC, Hydroelectricity

BC Hydro originally planned job fairs for the Site C project on July 28, 29, and 30 in Tumbler Ridge, Fort St. John and Chetwynd, respectively. These…