Independent review of Site C by Ernst & Young / BTY finds appropriate processes in place to meet project milestones and financial targets
VANCOUVER – BC Hydro today released an independent review of the Site C project’s risk and cost management processes by Ernst & Young LLP and BTY…

Letter: Site C will produce fewer GHGs than alternatives including wind and solar
Dear Editor, Contrary to what was stated in a column by Konrad Yakabuski, the Site C project in B.C. is being built to meet domestic electricity needs…

BC Hydro announces shortlist for generating station and spillways civil works
VANCOUVER – BC Hydro today announced the four proponent teams that have been shortlisted for the generating station and spillways civil works contract…

BC Hydro establishes $800,000 fund to support non-profits in Peace Region
FORT ST. JOHN – BC Hydro today launched an $800,000 fund to support Peace Region non-profit organizations. The Generate Opportunities (GO) Fund will b…

BC Hydro releases framework for the Agricultural Mitigation and Compensation Plan
$20 million agriculture compensation fund reflects regional input DAWSON CREEK – BC Hydro today released the framework for the Agricultural Mitigation…

BC Hydro responds to Amnesty International Report
FORT ST. JOHN – BC Hydro provided a response today to an Amnesty International report about Site C. BC Hydro has a world class system that is 98 per c…

Site C construction reaches one year
FORT ST. JOHN – Construction of the Site C project in northeast British Columbia reached its one-year anniversary last week. Significant construction…

BC Hydro and Dene Tha’ First Nation come to agreement on Site C
VANCOUVER – BC Hydro and Dene Tha’ First Nation have concluded an agreement related to the construction and operation of the Site C Clean Energy Proje…

1,200 rooms now open at Site C worker lodge
Second of three phases completed on schedule and on budget FORT ST. JOHN – BC Hydro and its contractor, ATCO Two Rivers Lodging Group, have reached a…

Site C reaches employment milestone surpassing 1,000 B.C. workers
FORT ST. JOHN – There are now more than 1,000 British Columbians working on the Site C Clean Energy Project, according to BC Hydro’s latest employment…